OJVG UPGRADES SABODALA GOLD PROJECT
FEASIBILITY STUDY
HIGHLIGHTS
• OJVG Undertaking a Higher Level Feasibility Study Than Initially Planned
• Q2 2010 Resource Update to Form Basis of Upgraded Feasibility Study
• Four Drills Assigned to Feasibility Engineering and Geotechnical Drill Program
• Three Additional Drills Being Mobilized to Continue Advanced Exploration and
Resource Drilling
Oromin Explorations Ltd.

("Oromin"), on behalf of the Oromin Joint Venture Group ("OJVG"), is
pleased to provide an update with respect to the feasibility study on its Sabodala Gold Project in
eastern Sénégal, West Africa.

OJVG has increased the scope and technical level for this feasibility
study.

This will result in it representing a significantly higher level study than the August 2009
preliminary feasibility study and will be more than simply an optimization of the previous study.
This upgraded feasibility study is on schedule for completion by the end of June 2010.

The study,
estimated to cost approximately $3.2 million exclusive of geotechnical drilling and environmental
permitting costs, is being prepared by SRK Consulting and Ausenco Limited.

The objective of the
upgraded study is to permit OJVG to fast track development of the Sabodala Gold Project.
Since the completion of the August 2009 study, technical efforts have focussed on updating the
resource models and optimizing the project concept.

Work to be undertaken from this point
onward will refine engineering designs and associated cost estimates.

Aspects of the study
completed or currently underway include the following:
o Resource models for Masato, Golouma South, and Kerekounda deposits will have been
updated with recent drill results by month end.

The resource models for Golouma West
and Kourouloulou deposits will be updated in February following receipt this month of the
outstanding assay results from 2009 drilling.

These five deposits will form the basis for the
production schedule and project economics to be outlined in the feasibility study.
o Detailed geotechnical investigations will be completed for Golouma West, Golouma South,
and Kerekounda by month end and are in progress on the other deposits.

In order to fast
track OJVG"s geotechnical investigations, three core drill rigs and one reverse circulation
drill rig have been reassigned from exploration drilling to undertake this very important
Page 2 of 3
geotechnical work.

These site investigations supplement previous geotechnical surveys
and address pit slope stability, underground mine stability, tailings dam and water reservoir
dam designs and plant site foundations.

Borrow pit areas required to provide construction
earth fill are also being delineated.

The entire geotechnical investigation will be completed
by early March and will permit preparation of the detailed earthworks designs.
o Three additional drills are being mobilised for OJVG"s ongoing resource delineation
program.

In addition to the five deposits referred to above that will form the basis for the
feasibility production schedule, the study will also report resources for two other deposits;
Maki Medina and Niakafiri and, time permitting, the Kobokoto and Koulouquinde
prospects.

Also, OJVG is working towards reporting resources for an additional two new
discoveries, Golouma Northwest and Kotouniokolla, after completion of the feasibility
study.
o In house trade-off studies have been completed examining mining sequences and mill
throughput rates and these have been used to provide direction on the feasibility production
scheduling.

The Masato-style bulk tonnage deposits (Masato, Niakafiri and Maki Medina)
will be developed via open pit mining only, while the Golouma-style high grade deposits
(Golouma South, Golouma West, Kerekounda, Kourouloulou) may entail both open pit and
underground mining aspects.

For these latter deposits, the economic transition points
between open pit mining and underground mining are currently being examined on an
individual basis to optimize the mine designs and enable the recovery of additional ore at
depth below the pits.
o The metallurgical testing database has been supplemented with additional test work for all
the deposits, including column leach tests on Masato oxide ore.

Grind size optimization
tests have also been undertaken and confirm that process recoveries in the range of 90 to
96% are realistic.
o The mill flowsheet redesign has been completed based on the metallurgical test work.

The
process flowsheet has been simplified and optimized from that presented in the August
2009 study to reduce capital and operating costs yet maintain performance.

The gravity
circuit is no longer required as the CIL-only process recoveries are very encouraging.

In
addition, it is now recognized that the milling of near surface soft ore will allow an
increased mill throughput compared to that when milling hard ore.

The nominal mill
capacity will be in the range of 4400 tonnes per day but can be increased to about 7000
tonnes per day when processing soft ore.

This would increase gold production revenue in
the early years of the project when the soft ore is encountered.
o Other engineering related activities currently nearing completion include issuing the
pricing quotation requests for major equipment and updating the feasibility level mining
and milling operating costs.
o Environmental baseline studies are progressing in the disciplines of hydrology,
archaeology, vegetation, and sustainable development planning.

These studies form part of
the Environmental Impact and Social Assessment that will be completed during 2010.
Page 3 of 3
Ken Kuchling, P.Eng., a "qualified person" for the purposes of National Instrument 43-101, has
verified the information disclosed in this news release.
Oromin is pleased with the progress made during the last few months and looks forward to
completion of the feasibility study in June.
On behalf of the Board of Directors of
OROMIN EXPLORATIONS LTD.
"Chet Idziszek"_________
Chet Idziszek, President
Cautionary Statement
This document contains "forward-looking statements" within the meaning of applicable Canadian securities regulations.

All statements other than
statements of historical fact herein, including, without limitation, statements regarding exploration plans and our other future plans and objectives,
are forward-looking statements that involve various risks and uncertainties.

Such forward-looking statements include, without limitation, estimates
of exploration investment and the scope of exploration programs.

There can be no assurance that such statements will prove to be accurate, and
future events and actual results could differ materially from those anticipated in such statements.

Important factors that could cause actual results to
differ materially from our expectations are disclosed in the Company"s documents filed from time to time via SEDAR with the Canadian regulatory
agencies to whose policies we are bound.

Forward-looking statements are based on the estimates and opinions of management on the date the
statements are made, and we do not undertake any obligation to update forward-looking statements should conditions or our estimates or opinions
change.

Forward-looking statements are subject to risks, uncertainties and other factors, including risks associated with public markets, mineral
exploration, price volatility in the mineral commodities we seek, and operational and political risks.

Readers are advised not to place undue reliance
on forward-looking statements.




Products & Services | Jobs