🕐22.01.10 - 02:18 Uhr

Pike River Quarterly Activities Report - quarter ended 31 Dec 09



1
Pike River Coal Limited
Activities Report
Quarter ended 31 December 2009*
First Export Shipment
Pike River Coal"s first export shipment of 20,000 tonnes of premium hard
coking coal is due to depart Lyttelton in February 2010.

One of Pike River"s
Indian customers will be the recipient of this inaugural cargo which has a value
of approximately NZ$3.4 million.

Pike River"s second export shipment, scheduled
for the April - June 2010 quarter, will be around 40,000 tonnes.
Trucking of coal from Pike River"s Coal Preparation Plant to the new rail load out facility at Ikamatua has begun in preparation for the first export shipment of hard coking coal.

The coal transport chain is shown below.
* This Activities Report covers activities for the quarter ended 31 December 2009 with some updates to 21 January 2010 where relevant.
Key Points
• First Export Coal
Shipment scheduled for
February 2010
• Roadways Driven through Rock Graben by early February
• In-seam Drilling giving Good Results
• Hydro-Mining
Production scheduled
for Jul-Sep 2010 quarter
• Hard Coking Coal Spot Price at US$180 per tonne
Pike River Coal"s first export shipment is due to depart Lyttelton in February 2010
Coal loading at the coal preparation plant
Coal
PreparationPlantCoalStock PilesTruck 22km toIkamatuaRail 250kmto Lyttelton2km Tunnel10km Slurry PipelinePit BottomLytteltonShip Loading,Port Lyttelton, East Coast1356
Operations
2
Roadways have now been advanced through 106 metres of rock ...

in a faulted zone (graben)
Continuous Miner Improvements
In December 2009 Pike River announced that one of its continuous miners was returned to the mine face after a software upgrade to the new traction system.

The upgrade was the final step in ensuring that this piece of machinery was fully operational.

The continuous miner"s performance has improved as expected for the conditions being encountered.

Similar modifications were made to the second continuous miner which is ready to return to service as soon as a coal face is available for cutting.

The continuous miners and the roadheader are the machines that cut coal to create mine roadways.

Drill and blast operations are used where roadways need to be constructed through rock.

Once the roadways have been constructed through the rock graben, all three machines will be in operation.
Progress Through Graben
Progress was made in ‘drill and blast" construction of roadways through the
rock graben immediately ahead of pit-bottom during the December quarter.
Roadways have now been advanced through 106 metres of rock (with a total of
269 metres of roadway construction in several headings) in a faulted zone (graben) with around 40 metres to cross before the roadway is back in coal.

The graben was encountered immediately to the west and north of pit bottom last year by the underground in-seam drilling unit.

Recent in-seam drilling to the north shows the graben to be approximately 150 metres wide.

Completion of this part of the process by early February 2010, will allow direct access to the main hydro-mining areas in preparation for the commencement of hydro-mining production.
In-Seam Drilling Giving Good Results
In-seam drilling continues with the most notable result being the progress made with in-seam drill holes from the northern pit-bottom area to the first hydro-mining panels.

As reported in the September quarterly update, one in-seam drill hole was completed in October to the western boundary of the graben and drilled a further 400 metres into the coal seam without intersecting any faulting.

In the December quarter, a further in-seam drill hole was completed north of the current stone drives to intersect the western graben boundary.

The current in-seam drill hole, targeting further north into the next hydro-mining area (to be mined 3 - 6 months after the initial panels)
has now progressed to 378 metres and is delivering good information to update
and validate the mine"s geological model.
PIKE RIVER COAL LIMITED
Export-ready coal prior to railing from Ikamatua to Port Lyttelton
Trucking of coal to Ikamatua has begun in preparation for the first export shipment
3
PIKE RIVER COAL LIMITED
ACTIVITIES REPORT
QUARTER ENDED 31 DECEMBER 2009
Ramp-up to Hydro-Mining
Infrastructure needed for hydro-mining continued to be developed
underground during the period.

The first of the two mobile coal receiver/crushers
("Guzzler") was dispatched from Australia to the mine site in January 2010 along
with the mobile roof support housing the high pressure coal cutting monitor.
Other equipment not already on-site is tracking to schedule.
First hydro-mining was forecast in the company"s August 2009
announcement for April-June 2010 quarter.

Timing of first hydro-mining is dependent upon advance rates achieved through the graben, construction of raw coal sumps in that stone area and access roadways through coal.

Commissioning of the hydro-mining system is now scheduled for June/July 2010.

The impact is to defer approximately 120,000-150,000 tonnes of coal production to the July-September 2010 quarter.
Work Force
Following on from the recruitment of a new Production Manager
(Michael Lerch) at the end of last year, Pike River has recently welcomed
a highly experienced Operations Manager (Doug White) to the now
11-member management team.
Pike River has full recruitment of 150 staff required for the current stage
of operations.

The final recruitment phase will begin shortly and will bring
on around 10 more staff mostly to support hydro-mining operations.
This quarter saw the completion of the initial trainee miner programme with 15 of our original 18 recruits completing their one-year training
and being promoted to full miner status.
Three medically treated injuries, none serious, occurred during the December quarter.
Environmental
Pike River"s pest and predator eradication programme, designed to create
a safe habitat for native birds, resulted in 17 stoats and 229 rats being
exterminated in the December quarter.

Pike River strives to achieve
industry best practice in environmental management.

No significant
environmental incidents occurred in the December quarter.
International Coal Market
and Coal Prices
Pike River"s first export shipment coincides with a buoyant and encouraging international market in which world coking coal prices are expected to rise even higher than previously forecast.

International market observers anticipate that premium hard coking coal prices could rise by 40% from April 2010 (JFY 2010) to US$180 per tonne.

China is again driving demand and is expected to import more than 20 million tonnes of hard coking coal (premium and standard grades) in the 2010 calendar year.

India, which is also heavily reliant on high grade coking coal imports to feed its steel-
The Guzzler (mobile coal receiving and crushing unit)
Pike River employee certified as full miner
...

premium hard coking coal prices could rise by 40% from April 2010 (JFY 2010) to US$180 per tonne
4
manufacturing industry, is increasingly becoming a major player in the market.

India is also projected to import more than 20 million tonnes of hard coking coal in the 2010 calendar year, including more than six million tonnes of premium hard coking coal.

Pike River is well-placed to benefit from the current international demand.
Note: Coal price data and China/India projections from MinAxis Pty Limited, January 2010.
Financing
The Pike River Board has been addressing the alternatives available for providing
the necessary working capital and further details are due to be released in the
next few weeks.
Emissions Trading Scheme
Parliament passed an act to revise the Emissions Trading Scheme (ETS) in November 2009.

Under this legislation, Pike River is a mandatory participant in the ETS and will be subject to carbon costs on fugitive gas emissions from 1 July 2010.

Pike River will measure actual emissions and apply for a unique emission factor as emissions from the Pike River mine are expected to be about one-quarter of the default levels otherwise used to calculate liabilities.
Gordon Ward
+64 4 494 0190
Chief Executive and
Managing Director
Peter Whittall
+64 3 769 8400
General Manager Mines
For Further Information
Pike River website: www.pike.co.nz
For Electronic Reports
Investors should register at:
www.pike.co.nz/email_alerts.php
to receive reports, news releases and other company
announcements via email on the day they are released.
Coal stockpile awaiting delivery to rail loadout facility at
Ikamatua
Pike River is well-placed to benefit from the current international demand




Products & Services | Jobs